Scope of Works

Project Overview: 

WSW Refurbishments, renowned for its expertise in educational institution refurbishments, completed a two-phase project at Matthew Arnold School in Middlesex. The project entailed replacing windows and roofing. 

Client Requirements: 

The project aimed to enhance the school’s infrastructure, ensuring a safer and more comfortable environment for learning and activities.

Scope of Works: 

1. Window and Curtain Wall Replacement

The first phase focused on replacing outdated windows and curtain walls with modern, energy-efficient solutions. This upgrade aimed to improve thermal insulation, enhance natural lighting, and give the school buildings a contemporary look.

2. Changing Room Roof Replacement

The changing room roof included installing a new, durable roofing system. Additionally, a fall arrest system was incorporated to ensure maintenance safety.

3. Installation of Fall Arrest System

A critical safety upgrade included installing a fall arrest system on the new roof. This system is designed to prevent falls and ensure the safety of maintenance workers when performing roof inspections or repairs.

4. Project Execution - Planning and Preparation

The project required planning to ensure it was completed within the school holidays.

5. Implementation

Window and Curtain Wall Replacement: The first phase began with carefully removing old windows and curtain walls. New, energy-efficient windows and curtain walls were installed, enhancing the school buildings' aesthetic appeal and functionality. The latest installations provided better insulation, reducing energy costs and improving the learning environment with enhanced natural light.

6. Changing Room Roof Replacement and Fall Arrest System Installation

The second phase involved removing the old roof and installing a new, robust roofing system for the changing rooms. The roof replacement was completed with high-quality materials to ensure longevity and durability. A fall arrest system was installed to provide a safe working environment for maintenance staff, complying with all relevant safety standards.

Results and Outcome: 

The project was completed on time and to a high standard. To minimise disruption, the refurbishment was completed outside of term time. It was planned and executed during the out-of-school term to minimise disruption to students and staff.